| By Adam Wenner and Cory Lankford On March 19, 2015, the Federal Energy Regulatory Commission 
            (FERC) issued Order No. 807, a rule that makes it easier for 
            developers of non-utility transmission lines that connect power 
            projects to the grid to avoid having to offer unused capacity on 
            those lines to third parties.  The rule also waives open-access 
            transmission related obligations that otherwise apply to 
            transmission owners.  When generation developers build new 
            power plants, they ordinarily construct and own new interconnecting 
            power lines – called "gen-tie lines" – and related equipment, such 
            as substations, referred to as "Interconnection Customer's 
            Interconnection Facilities" (ICIF) in FERC parlance.  In many 
            instances, these gen-tie lines are a few hundred feet, but for 
            solar, wind and geothermal plants, which are often located in less 
            populated areas, they can extend dozens or even hundreds of 
            miles. FERC's open access policies require owners of transmission lines 
            to function as common carriers by making unused capacity available 
            to third parties.  They also require transmission owners to 
            maintain websites providing information on transmission availability 
            (Open Access Same-Time Information System - OASIS) and impose 
            "Standards of Conduct" requirements that the transmission owner's 
            power sales functions be separated from its transmission 
            activities.  Under FERC's prior policies, gen-tie owners had to 
            file case-specific requests for waivers of OASIS obligations and 
            Standards of Conduct.  Also, upon receipt of a request for 
            transmission, FERC would require the gen-tie owner to file an Open 
            Access Transmission Tariff (OATT) and provide transmission service 
            to the requesting party, unless the owner could demonstrate to FERC 
            that it had developed specific plans to construct generation that 
            would use the excess transmission capacity and that it had made 
            material progress toward meeting its scheduled construction 
            milestones for development.  For developers who have borne the risk of developing and 
            financing these lines, these open access requirements have been 
            problematic, imposing costs and regulatory burdens and limiting 
            their incentive to undertake the risk of development only to have a 
            competitor wait on the sidelines and then obtain priority rights to 
            use transmission capacity on the ICIF if the developer successfully 
            completes it. The rule adopted by FERC provides a blanket waiver from the open 
            access requirements to eligible ICIF owners and establishes a 
            five-year "safe harbor" from the date that ICIF are first used for 
            commercial sales, during which there is a rebuttable presumption 
            that the ICIF owner has specific plans to use the ICIF.  After 
            the five-year period, third parties can seek to interconnect their 
            facilities with the ICIF by filing with FERC a request for 
            interconnection under Sections 210 and 211 of the Federal Power Act 
            (FPA), which is a much more burdensome process than the current 
            process of simply making a request for interconnection to the ICIF 
            owner. Background FERC's former policies imposed burdensome requirements on ICIF 
            owners by awarding priority to use available capacity on 
            interconnection facilities based on the timing of an interconnection 
            request.  It is common for generation developers to have excess 
            capacity on their interconnection facilities because they plan to 
            develop their generation facilities in phases, or because economies 
            of scale in transmission provide incentives to develop ICIF with 
            more capacity than is immediately needed, which is available for 
            future projects that the developer or its affiliates might 
            pursue.  Because FERC's policies encouraged transmission access 
            on a first-come, first-served basis, developers have been exposed to 
            the risk of a third-party request for service that could interfere 
            with the developer's planned use of its interconnection 
            facilities.   As discussed in more detail below, FERC has adopted three key 
            revisions to its policies relating to third-party use of 
            interconnection facilities that are intended to reduce regulatory 
            burdens and costs to generation developers, while ensuring open 
            access by permitting third-party interconnections only when they are 
            in the public interest.       
             Blanket Waiver In its final rule, FERC amends its regulations to grant a blanket 
            waiver of its open access requirements to any public utility that is 
            subject to such requirements solely because it owns, controls, or 
            operates ICIF.  FERC determined that "[s]uch a waiver is 
            justified because the usually limited and discrete nature of ICIF 
            and ICIF's dedicated interconnection purpose means that such 
            facilities do not typically present the concerns about 
            discriminatory conduct that [FERC's open access requirements] were 
            intended to address."  In addition, FERC stated that its 
            "existing policy [created] too low a bar for third-party requests 
            for service."   Under FERC's new approach, the blanket waiver from the open 
            access requirements will not be automatically revoked by a 
            third-party request for service over the ICIF.  Rather, a 
            third-party must file a petition with FERC under Sections 210, 211, 
            and 212 of the FPA, requesting FERC to direct the ICIF owner to 
            provide transmission.  FERC will grant such access only if the 
            request satisfies numerous criteria set forth in the FPA, including 
            a demonstration that it is in the public interest to give the 
            third-party request priority over the developer's planned use of the 
            excess capacity.  Accordingly, under FERC's new approach, it 
            will be much more difficult for a third-party to obtain 
            interconnection rights over the objection of the ICIF 
            owner.    Initially, FERC proposed to offer the blanket waiver only to 
            generator owners that also own ICIF, and not to independent gen-tie 
            owners.  FERC reasoned that this limitation was necessary to 
            ensure that the ICIF owners were subject to the mandatory 
            interconnection requirements set forth in Sections 210, 211, and 212 
            of the FPA, which apply to generator owners that make wholesale 
            sales of energy.  Importantly, Section 210 only authorizes FERC 
            to require an "electric utility" – defined as an entity that 
            sells electricity – to interconnect if FERC determines that such 
            interconnection is in the public interest.  However, many 
            generation developers prefer to establish a separate entity that 
            does not sell electricity to own, operate, and manage the 
            ICIF.  Accordingly, FERC expanded the definition of eligible 
            ICIF owners to include ICIF owners that do not sell electricity, 
            provided that they file with FERC a statement that they commit "to 
            comply with and be bound by the obligations and procedures 
            applicable to electric utilities under section 210 of the FPA." 
                 Safe Harbor The final rule also adopts a five-year safe harbor period during 
            which there is a "rebuttable presumption" that the ICIF owner has 
            definitive plans to use its capacity without having to make a 
            demonstration through a showing of specific plans and 
            milestones.  During the safe harbor, in order to overcome the 
            presumption, a third-party requesting service over ICIF must submit 
            evidence showing that the ICIF owner does not have definitive plans 
            to use its capacity and demonstrate that, under Sections 210 and 211 
            of the FPA, it is in the public interest to grant it priority rights 
            to use the ICIF capacity.  In response, the ICIF owner can 
            defend its priority through a showing of specific plans and 
            milestones to use the ICIF.  FERC states that, under this 
            approach, the "ICIF owner gains a degree of protection through the 
            reduced likelihood that a third-party requester could rebut the 
            presumption that an ICIF owner has plans to use of its capacity." 
              To take advantage of the safe harbor, ICIF owners must file with 
            FERC an informational notice stating: (1) the ICIF commercial 
            operation date, (2) sufficient detail to identify the ICIF, 
            including location and point of interconnection, and (3) 
            identification of the ICIF owner(s).  The five-year safe harbor 
            period starts on the date that the ICIF are first used to transmit 
            energy for sale, excluding use for on-site testing and commissioning 
            of the planned generating facility (i.e., the commercial 
            operation date of the first project to use the ICIF).  For ICIF 
            that are already in operation, the ICIF owner can still file a 
            notice to obtain a safe harbor to expire on the fifth anniversary of 
            the ICIF commercial operation date.   Interconnection Pursuant to FPA Sections 210 and 
            211 Following the safe harbor period, third parties can use 
            procedures set forth in Sections 210 and 211 of the FPA to request 
            interconnection with interconnection facilities that are subject to 
            the blanket waiver.  Under Section 210 of the FPA, FERC can 
            require ICIF owners to interconnect a third-party generating 
            facility if FERC determines that such interconnection is in the 
            public interest and would encourage conservation of energy or 
            capital, optimize efficient use of facilities and resources, or 
            improve reliability.  Similarly, under Section 211 of the FPA, 
            FERC can require ICIF owners to provide transmission service to 
            third parties if FERC determines that ordering such transmission 
            service is in the public interest.  The third party must 
            compensate the ICIF owner for the costs of any expansions required 
            to interconnect and provide transmission service to the third 
            party.  FERC precedent is unclear, however, on whether a third 
            party must compensate the interconnection facility owner for 
            incremental line losses caused by the third-party 
            interconnection.     The final rule will be published in the Federal Register within 
            the next few weeks, and will become effective 90 days later.  
            Accordingly, FERC will accept informational filings from ICIF owners 
            to claim their safe harbor rights beginning in July 2015, if not 
            sooner.    A copy of Order No. 807 can be found here.  
            For more information about this matter, please contact:  Adam 
            WennerPartner
 [email protected]
 (202) 
            339-8515
 
 Cory 
            Lankford
 Managing Associate
 [email protected]
 (202) 
            339-8620
 |